Pipeline Delivery Station Gas Heating Project

Two 100 kW heating skids arranged for duty and standby service at a natural gas delivery point.

Project overview

Application and supply scope.

The project configuration below summarizes the supplied equipment and its process application.

Year
2024
Region
Hunan, China
Application
Gas delivery and pressure-reduction heating
Supply scope
Two integrated electric heater skids
Installed electric gas heating skids and station piping
Electric heating skids installed with the station piping.
The engineering challenge

Conditions shaping the heating duty.

Pressure-reduction cooling at a new pipeline delivery point created hydrate and freeze-blockage risks for downstream station equipment.

The site required hazardous-area equipment, continuity of gas supply and local operation with remote visibility.

Equipment configuration

What the package includes.

Equipment capacities, interfaces and controls are matched to the project application.

Installed arrangement
2 × 100 kW; one duty + one standby
Equipment
Vertical explosion-proof resistance heater skids
Control
Local HMI; automatic outlet-temperature regulation
Communication
RS485 Modbus RTU / SCADA
Field configuration
Ex d IIB T4 Gb; IP65
Protection
Two-stage overtemperature, low flow, pressure relief and electrical protection
Package scope & interfaces

Beyond the heater body.

The integration and handover scope documented for this project.

Skid assembly

Two 100 kW heater skids with piping, valves, relief equipment and instruments.

Electrical & controls

Junction boxes, control cabinets, local HMI and outlet-temperature regulation.

Plant interfaces

Defined mechanical and electrical boundaries with RS485 Modbus RTU / SCADA communication.

Our approach

Engineering the complete heating package.

Duty and standby arrangement

Two complete 100 kW skids allow standby availability for maintenance or protected shutdown, subject to the station operating strategy.

Factory-integrated supply

The scope includes heater bodies, piping, valves, relief equipment, instruments, junction boxes and control cabinets, giving the site a defined mechanical and electrical connection boundary.

Temperature and protection logic

Closed-loop outlet-temperature control is combined with staged overtemperature and low-flow protection. Modbus communication supports setpoint exchange, power feedback, alarms and status monitoring.

Project value

Delivery and application value.

Process objective

The packages provide temperature compensation around pressure reduction to reduce hydrate and ice-blockage risk and support downstream valves and instruments.

Delivery value

Integrated skid supply reduces dispersed site assembly. No quantified availability or commissioning-time improvement is claimed in this summary.